Our E.P.C. wrapped delivery for this project encompasses a broad scope of activities including demolition and ground-works, detailed civil and process design, pre-treatment equipment, waste reception building, biogas plant construction and electrical grid connection.
Project Details
Client
Farleigh Biogas
Location
Basingstoke, Hampshire, UK
Further Information
AD Plant Details Summary
- Processing capacity 50,000tpa
- 2 x 1,800m³ primary digesters
- 1 x 1,400m³ secondary digester
- 3 x 4,500m³ end storage tank
- 1 x 500m³ Buffer Tank
- 2 x 8t/h foodwaste depackaging lines
- 35m x 28m x 12m Reception Building
- 1 x 1,500 kWe CHP
- 3 x 10m³ Batch Pasteurisers
- Odour Abatement System
- Weighbridge
- Site Office
Feedstocks
Packaged and source separated food waste plus waste organic liquids
Biogas Utilisation
- Electricity to grid
- 1.5 MWe CHP
- LV connection/distribution
- Transformer
- HV Substation connection
Civil Engineering & Design
All site civil engineering works and civils design carried out by FLI Energy
- Site Clearance & Demolition
- Site Access Road
- Waste Reception Building
- Site Bunding and Containment
- Site Drainage
- Site Hardstanding